A company has budgeted total overhead of $10,575 at actual units produced and actual total overhead of $9,775. The controllable variance is:

Study for the Accounting Test. Prepare with flashcards and multiple-choice questions, each question includes hints and explanations. Get ready for your exam!

Multiple Choice

A company has budgeted total overhead of $10,575 at actual units produced and actual total overhead of $9,775. The controllable variance is:

Explanation:
In overhead variance analysis, the controllable variance shows how well overhead costs were managed relative to what was planned for the actual level of production. Here, the company budgeted total overhead of 10,575 for the actual units produced, while the actual overhead incurred was 9,775. The difference is 10,575 − 9,775 = 800. Since actual spending is lower than the budget, this is a favorable variance, meaning overhead costs were controlled under plan. Therefore, the correct result is 800 Favorable.

In overhead variance analysis, the controllable variance shows how well overhead costs were managed relative to what was planned for the actual level of production. Here, the company budgeted total overhead of 10,575 for the actual units produced, while the actual overhead incurred was 9,775. The difference is 10,575 − 9,775 = 800. Since actual spending is lower than the budget, this is a favorable variance, meaning overhead costs were controlled under plan. Therefore, the correct result is 800 Favorable.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy